DaimlerChrysler Reports Plant Schedule for Week of January 24, 2000

21 January 2000

DaimlerChrysler Corporation Reports U.S. and Canadian Assembly Plant Schedule for Week of January 24, 2000
    AUBURN HILLS, Mich., Jan. 20 -- DaimlerChrysler Corporation
reports all nine U.S. assembly plants and all three Canadian
assembly plants will operate the week of January 24, 2000.
    Jefferson-North (Detroit, Mich.) will operate three seven-and-a-half hour
shifts during the week.  Belvidere (Ill.), St. Louis-North (Fenton, Mo.) and
St. Louis-South (Fenton, Mo.) will operate two eight-hour shifts.  Conner Ave.
(Mich.) will operate one-eight-hour shift.  Sterling Heights (Mich.) and
Toledo (Ohio) will operate two eight-hour shifts during the week and two
eight-hour shifts on Saturday, January 22.  Dodge City Complex-Warren Truck
(Mich.) will operate two nine-hour shifts during the week and two eight-hour
shifts on Saturday, January 22.  Newark (Del.) will operate two nine-and-a-
half hour shifts during the week and two eight-hour shifts on Saturday,
January 22.
    In Ontario, Canada, the Windsor Assembly Plant will operate three seven-
and-a-half hour shifts during the week and three seven-and-a-half hour shifts
on Saturday, January 22.  Bramalea will operate three seven-and-a-half hour
shifts.  Pillette will operate two eight-hour shifts.