13 August 1999

DaimlerChrysler Corporation Reports U.S. and Canadian Assembly Plant Schedule For Week of August 16, 1999
    AUBURN HILLS, Mich., Aug. 12 -- DaimlerChrysler Corporation
reports all nine U.S. assembly plants and all three Canadian
assembly plants will operate the week of August 16, 1999.
    Jefferson-North (Detroit, Mich.) will operate three seven-and-a-half hour
shifts during the week.  Dodge City Complex-Warren Truck (Mich.), Newark
(Del.), St. Louis-South (Fenton, Mo.), Sterling Heights (Mich.), and Toledo
(Ohio) will operate two eight-hour shifts.  St. Louis-North (Fenton, Mo.) will
operate two nine-hour shifts.  Conner Ave. (Mich.) will operate one-eight-hour
shift.  Belvidere (Ill.), will operate two eight-hour shifts during the week
and one eight-hour shift on Saturday, August 14.
    In Ontario, Canada, the Windsor Assembly Plant will operate three seven-
and-a-half hour shifts during the week and three seven-and-a-half hour shifts
on Saturday, August 14.  Bramalea will operate three seven-and-a-half hour
shifts.  Pillette will operate two eight-hour shifts.