DaimlerChrysler Plant Schedule For Week of November 30, 1998

26 November 1998

DaimlerChrysler Corporation Reports U.S. and Canadian Assembly Plant Schedule For Week of November 30, 1998
    AUBURN HILLS, Mich., Nov. 25 -- DaimlerChrysler Corporation
reports seven of its nine U.S. assembly plants and all three
Canadian assembly plants will operate the week of November 30, 1998.
    Jefferson-North (Detroit, Mich.) will operate three seven-and-a-half hour
shifts during the week.  St. Louis-South (Fenton, Mo.) and Toledo (Ohio) will
operate two eight-hour shifts.  Dodge City Complex-Warren Truck (Mich.) and
St. Louis-North (Fenton, Mo.) will operate two nine-hour shifts.  Newark
(Del.) will operate two nine-and-a-half hour shifts.  Conner Ave. (Mich.) will
operate one eight-hour shift.  Sterling Heights (Mich.) will not operate due
to inventory adjustment.  Belvidere (Ill.) will not operate due to model
changeover.
    In Ontario, Canada, Bramalea and the Windsor Assembly Plant will operate
three seven-and-a-half hour shifts during the week.  Pillette will operate two
eight-hour shifts.