Chrysler Reports Assemble Plant Schedule For Week of Aug 31, 1998

28 August 1998

Chrysler Reports U.S. and Canadian Assembly Plants Schedule For Week of August 31, 1998
    AUBURN HILLS, Mich., Aug. 27 -- Chrysler Corporation
reports all nine U.S. assembly plants and all three Canadian
assembly plants will operate the week of August 31, 1998.  The three Canadian
plants will not operate Friday, September 4, due to the Labor Day holiday.
    Jefferson-North (Detroit, Mich.) will operate three seven-and-a-half hour
shifts during the week.  Belvidere (Ill.), Dodge City Complex-Warren Truck
(Mich.), Newark (Del.), St. Louis-North (Fenton, Mo.), Sterling Heights
(Mich.), and Toledo (Ohio) will operate two eight-hour shifts during the week.
Conner Ave. (Mich.) will operate one-eight-hour shift.  St. Louis-South
(Fenton, Mo.) will operate two nine-hour shifts during the week.
    In Ontario, Canada, Bramalea will operate three seven-and-a-half hour
shifts during the week and three seven-and-a-half hour shifts on Saturday,
August 29.  The Windsor Assembly Plant will operate three seven-and-a-half
hour shifts.  Pillette will operate two eight-hour shifts.