    AUBURN HILLS, Mich., Jan. 29 -- Chrysler Corporation
reports all nine U.S. assembly plants and all three Canadian
assembly plants will operate the week of February 2, 1998.
    Jefferson-North (Detroit, Mich.) will operate three seven-and-a-half hour
shifts during the week and three seven-and-a-half hour shifts on Saturday,
January 31.  Belvidere (Ill.), Dodge City Complex-Warren Truck (Mich.) and
St.Louis-South (Fenton, Mo.) will operate two eight-hour shifts.  Conner Ave.
(Mich.) will operate one eight-hour shift.  Sterling Heights (Mich.) and
Toledo (Ohio) will operate two eight-hour shifts during the week and two
eight-hour shifts on Saturday, January 31.  Newark (Del.) and St.Louis-North
(Fenton, Mo.) will operate two nine-hour shifts during the week and two
eight-hour shifts on Saturday, January 31.
    In Ontario, Canada, the Windsor Assembly Plant will operate three
seven-and-a-half hour shifts during the week.  Bramalea will operate two
eight-hour shifts.  Pillette will operate two eight-hour shifts during the
week and two eight-hour shifts on Saturday, January 31.