Chrysler Reports U.S. and Canadian Assembly Plants Schedule For Week of August 11, 1997
7 August 1997
Chrysler Reports U.S. and Canadian Assembly Plants Schedule For Week of August 11, 1997AUBURN HILLS, Mich., Aug. 7 -- Chrysler Corporation reports seven of its nine U.S. assembly plants and two of its three Canadian assembly plants will operate the week of August 11. Jefferson-North (Detroit, Mich.) will operate three seven-hour shifts during the week. Belvidere (Ill.), Dodge City Complex-Warren (Mich.), St. Louis-North (Fenton, Mo.), St. Louis-South (Fenton, Mo.), Sterling Heights (Mich.), and Toledo (Ohio) will operate two eight-hour shifts. Conner Ave. (Mich.) will not operate due to vacation. Newark (Del.) will not operate due to model changeover. In Ontario, Canada, Windsor Assembly Plant will operate three seven-and-a-half hour shifts during the week. Pillette will operate two eight-hour shifts during the week and two eight-hour shifts on Saturday, August 9. Bramalea will not operate due to model changeover. SOURCE Chrysler Corporation