Chrysler Reports U.S. and Canadian Assembly Plants Schedule For Week of July 21, 1997

17 July 1997

Chrysler Reports U.S. and Canadian Assembly Plants Schedule For Week of July 21, 1997

    AUBURN HILLS, Mich., July 17 -- Chrysler Corporation
reports seven of its nine U.S. assembly plants and all three
Canadian assembly plants will operate the week of July 21.
    Jefferson-North (Detroit, Mich.) will operate three seven-and-a-half hour
shifts during the week.  Belvidere (Ill.), Dodge City Complex-Warren (Mich.),
St. Louis-North (Fenton, Mo.), St. Louis-South (Fenton, Mo.), and Toledo
(Ohio) will operate two eight-hour shifts.  Conner Ave. (Mich.) will operate
one eight-hour shift.  Newark (Del.) and Sterling Heights (Mich.) will not
operate due to model changeover.
    In Ontario, Canada, Windsor Assembly Plant will operate three
seven-and-a-half hour shifts during the week.  Pillette will operate two
eight-hour shifts during the week and two eight-hour shifts on Saturday,
July 19.  Bramalea will operate two eight-hour shifts during the week, two
eight-hour shifts on Saturday, July 19, and two six-hour shifts on Sunday,
July 20.

SOURCE  Chrysler Corporation